Hardwood Floor Refinishing & Sanding in Marietta, GA
Floors are often one piece of a bigger update. If hardwood floor refinishing in Marietta is happening alongside new paint, fresh trim, a cabinet swap or stair work, the order of those jobs matters as much as the sanding itself. Get it wrong and a ladder scuffs the new finish, or the edger chews into baseboards that were caulked the week before.
Here is where refinishing usually fits, and how to keep the trades from undoing each other’s work.
Why floor finishing usually comes late in the schedule
As a rule, the dirtiest and heaviest work happens first and the most easily damaged surface is finished last. Drywall repair, demolition, cabinet installation and most wall painting bring dust, drips and foot traffic that a fresh floor finish does not need. Sanding starts once that work is done, so the final coats go down on a floor that will not see drop cloths and tool bags for a while.
There is a common exception. Some homeowners prefer to paint after the floor, because sanding dust settles on wet paint and edging can mark the bottom of the wall. Then the painter cuts in carefully along the baseboard and works over a cured finish with clean drop cloths. Either order works when everyone agrees on it in advance.
Baseboards, shoe molding and trim
Shoe molding, the small rounded strip at the base of the wall, is often pulled before sanding so the edger can reach the last inch of floor. It goes back afterward, and trim is typically caulked and touched up once the finish has cured. If you are replacing baseboards entirely, installing them after the floor avoids sanding marks on new paint, as long as the new trim is tall and thick enough to cover the gap at the wall.
Cabinets, appliances and stairs in the same project
When new kitchen cabinets are going in, decide early whether they will sit on the finished hardwood or whether the wood will simply run up to them. Setting cabinets first means the floor is sanded and edged up to the toe kick, which leaves a clean line but no finished wood underneath if the layout ever changes. Appliances return only after cure, moved on protective sheets rather than dragged.
Stairs are easier to coordinate when the treads are part of the same plan. Refinishing treads and floors together lets the stain carry from the landing into the hall, and our Marietta staircase remodeling work covers new treads, risers and railings when the steps need more than a fresh finish.
Checking the floor before dates are locked
None of the scheduling helps if the floor holds surprises. Peeling finish or gray, worn-through traffic paths mean the wood itself has been exposed and a full sanding is needed rather than a light recoat. Loose, cracked or water-damaged boards should be found now, so they are repaired before sanding and cut down with everything else. On a floor that has been sanded before, the remaining thickness above the tongue is checked so deep wear can come out without exposing nails.
Boards beyond saving are swapped for matching stock, and our page on hardwood floor installation and repair explains that carpentry in more detail.
Stain tone and the rest of the room
A remodel changes the surroundings the floor has to suit. New cabinet colors, wall paint and countertops all shift how a stain reads, so keep paint chips or a sample cabinet door nearby when test patches go down on the sanded boards. Expect the color to differ from a printed card, because species, grain and the final sanding grit all affect it. The finish on top matters too: oil-modified polyurethane warms the tone, a water-based product stays closer to the raw stain, and a satin or matte sheen softens the whole floor.
Sequence for the floor portion
- Other trades finish their dusty work and clear out of the rooms.
- Doorways are sealed with plastic and air returns are covered.
- Loose boards are fastened and damaged ones replaced.
- The floor is sanded through progressively finer grits, then edged and hand-scraped along walls, cabinets and doorways.
- After vacuuming, stain samples are approved and color goes on, if chosen.
- Finish coats go on one at a time, each lightly screened before the next.
- Shoe molding is reinstalled and touched up once the floor can take foot traffic.
Marietta permits and the written scope
Marietta lies within Cobb County. Sanding and finishing a floor is surface work, but a remodel that adds plumbing, electrical or structural changes is a different matter; for that part of the job, ask the City of Marietta Building Division about permits.
On the floor side, a useful quote names each room, the boards to be repaired or a set allowance, the color, the finish and how many coats it gets, and whether shoe molding is pulled and reset. Because several trades share the house, it should also say who covers the new floor once the last coat is down, who touches up trim, and how a change in plans gets signed off.
Frequently asked questions about refinishing during a remodel
Should I paint the walls before or after refinishing my hardwood floors?
Both orders work. Painting first means sanding dust and the edger can mark the lower wall, so a final baseboard touch-up is usually planned. Painting after means the painter works over a cured finish with clean drop cloths and careful cutting-in. Pick one approach, tell both trades and put it on the schedule so nobody shows up at the wrong point.
Do new kitchen cabinets go in before the floor is refinished?
Usually, yes. Cabinet installation creates dust and traffic, so setting the boxes first and refinishing afterward protects the new finish. The tradeoff is that the wood under the cabinets stays as it is, and edging along the toe kicks needs care. If the layout might change in the future, talk about whether finished flooring should run under the cabinet area instead.
Can my Marietta stairs be refinished at the same time as the floors?
Yes, and doing them together makes it easier to match the stain from the treads to the landing and hallway. Stairs take far more hand sanding than open floor, so they add time, and the household needs a plan for getting up and down while the finish dries. Keep the stairs in the same written scope so colors and coat counts line up.
Plan the floor with the rest of the project